Check the electrical package before pricing
Before inviting a bid for a fiberglass pool’s electrical package, total the materials, equipment, and labor in that portion of the project. Tennessee requires an electrical subcontractor contracting directly with a contractor to hold a contractor’s license when the electrical portion reaches $25,000. The license must be in place before the subcontractor bids, offers to take the work, or negotiates a price for the covered package.
Match the license to the company and scope
Get the credential type, number, and exact holder name. Search by number or by individual or business name within the license type. Compare the record with the entity that will sign, then check the status, any listed expiration date, applicable classification, and any monetary limit. If the record names an individual and the work order names a company, ask which credential covers the signing company. Send unresolved holder or scope questions to the Tennessee Board for Licensing Contractors. Confirm permit requirements at the job address with the local electrical permitting authority, including for work below $25,000.
Recheck scope changes and record the award
If added lighting and equipment connections raise the electrical package from $23,000 to $26,000, verify the required license before the subcontractor bids or negotiates the revised package. At award, save the dated lookup, verified holder and signing entity, credential details, final work order, and any confirmation that resolved a mismatch. Keep the award on hold while a material question remains open.