Lay out the 14-by-30 and 14-by-35 Aspen fiberglass pools
Thursday Pools lists outside shell dimensions of 14 by 30 feet and 14 by 35 feet. The manufacturer’s size table shows a “Download Dig Specs” entry beside each of those two sizes. [Thursday Pools Aspen sizes and dig specifications](https://thursdaypools.com/pool-designs/aspen/)
For the first comparison, draw both shells on the same centerline with their uphill ends at the same reference point. In that layout, the 35-foot shell extends five feet farther downhill. Plot each excavation footprint using the corresponding dig specifications, then mark the planned pool elevation for each option on the site sketch.
Check the grade break and delivery route
Thursday Pools’ Tennessee dealer survey identifies slope, soil conditions and restricted access as factors that can raise site-work costs. Latham’s fiberglass pool installation guide lists excavators, trucks and cranes among the equipment that may need yard access. [Thursday Pools Tennessee dealer survey](https://thursdaypools.com/blog/how-much-does-a-fiberglass-pool-cost-in-tennessee/) · [Latham installation guide](https://www.lathampool.com/blog/plan/timeline-for-building-a-fiberglass-pool/)
Say the 35-foot excavation crosses a grade break that the 30-foot excavation stops short of. Take existing ground elevations on both sides of the break and along the proposed dig limits. Compare those readings with each option’s planned pool elevation and excavation profile. Use that comparison to determine how much cut, fill and haul-off each layout requires before assigning a cost to the longer option.
Walk the delivery route with the provider for both layouts. Mark the truck turn, any crane setup area and the equipment exit. If a grading area overlaps the proposed crane setup, agree with both crews on what must be complete before delivery, what must stay clear through the shell set and what can wait until the equipment leaves.
Write the fixed price, grading allowance and change-order terms
**Fixed price.** Give each option its own price for the confirmed shell, excavation, grading, haul-off, delivery and set. Reference the dated site plan and list the grading limits and quantities included in that price. Any additional grading awaiting field confirmation belongs in a separate allowance outside the fixed-price scope.
**Grading allowance.** If field checks leave a quantity unresolved, identify the area and work the allowance covers. For example, carry 12 cubic yards of additional cut and haul-off beyond the fixed-price grading limits at the grading contractor’s quoted rate per cubic yard. Specify that the billable quantity is measured in place from before-and-after elevations within the marked allowance area, with haul-off included in the rate. Credit any unused quantity at that rate and reconcile approved overruns at the same rate.
**Written change order.** If field measurements show the work will exceed the allowance quantity, or if the delivery provider calls for staging changes that affect the scope, document the revised work, price and schedule. Obtain written approval before starting the affected work.
Confirm availability before quoting a summer 2027 schedule
Bring both layouts and dig specifications to the winter site walk. Ask the local dealer or supplier which sizes can be ordered, the current lead time for each and the order deadline for the proposed delivery window. Confirm crew dates and what must be ready before each crew mobilizes. Record those commitments and any pending dates in the spring proposal so the customer can see what the summer 2027 target depends on.