Give both bidders the same scope
Ask both bidders to price the same shell, equipment, and finished site. Use one comparison sheet for access, excavation, spoil removal, delivery, shell setting, decking, the barrier, equipment, first fill, and startup. Mark each line as fixed, an allowance, or excluded. Ask what delivery includes and who pays for unloading, crane service if needed, and setting the shell in the excavation.
Work through the difference in price
Suppose Bid A is $58,000, includes delivery and setting, and carries a $300 first-fill allowance. Bid B is $55,500, includes delivery to the site, and excludes shell setting, water, and startup. If both bids need $500 for the same fill arrangement, add $200 to Bid A. If the contractor confirms $2,800 for setting and $400 for startup on Bid B, add those costs and the full $500 for water. With startup included in Bid A and the other scope matched, the comparison is $58,200 versus $59,200. These figures are illustrative.
Confirm who supplies water and starts the equipment
Put the selected water source, booking responsibility, and rescheduling charges beside the fill amount. For properties served by Murfreesboro, the city lists a garden hose and a hydrant-meter rental as fill options.
Ask whether startup covers equipment setup and an owner walkthrough. Keep the final scope and price under the contracting business name. Tennessee’s license verification service lets you check an individual or company for a valid state license.